LK GREEN CAPITAL

Frontier AI datacentre

Vantage TX1

Vantage TX1, is a frontier AI datacentre in the United States with
32 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
of IT power online and
128 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
planned by Aug 2027. That is 25% of its planned capacity (calculated), per Epoch AI's register on 14 Oct 2026.

Vantage TX1 among the largest sites in the United States

IT power online now and planned
Vantage TX1 and comparable frontier AI datacentres, largest planned first
SiteOwnerUsersCountryOnline nowPlanned Planned date
Microsoft Fairwater WisconsinMicrosoftOpenAI, MicrosoftUnited States
369 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
est. at 15 May
2.26 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
13 May 2028
Anthropic-Amazon New CarlisleAmazonAnthropicUnited States
910 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
est. at 3 Jun
1.93 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
17 Mar 2028
OpenAI Stargate New MexicoOracleOpenAIUnited States
0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
est. at 22 Jun
1.75 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
31 Dec 2028
Meta HyperionMetaMetaUnited States
0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
est. at 19 Apr
1.63 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
1 Jan 2028
Colossus 2SpaceXAIAnthropic, Cursor, SpaceXAIUnited States
946 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
est. at 15 Jun
1.53 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
25 Feb 2027
OpenAI Stargate ShackelfordOracleOpenAIUnited States
0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
est. at 4 Sep
1.40 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
11 Nov 2028
QTS Cedar RapidsNot statedNot statedUnited States
0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
est. at 7 May
1.13 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
15 Nov 2027
Vantage TX1Not statedNot statedUnited States
32 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
est. at 15 Feb
128 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
31 Aug 2027

Site details

Owner
Not stated
Users
Not stated
IT power online now
32 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
estimate at 15 Feb 2026
Largest planned IT power
128 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source
Planned date
31 Aug 2027

Latest construction note

Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, based on the appearance, we believe it is operational. Reported IT

Note from Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0).

Questions

How much power does Vantage TX1 have?

32 MW of IT power was online at the latest estimate in the register, against 128 MW planned, 25% of the plan (calculated). Snapshot of 14 Oct 2026.

When will Vantage TX1 be finished?

Epoch AI's timeline puts the site's largest planned IT power, 128 MW, at Aug 2027. Timelines are estimates and change as construction progresses.

Where does this datacentre data come from?

Epoch AI's Frontier Data Centers register (CC BY 4.0), which estimates each site's IT power over time from satellite imagery, permits and company statements. Figures are estimates, not company specifications.

Updated 14 Oct 2026. Source: Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0). Estimates, not company specifications. Methodology: Pipeline Tracker. Not investment advice.

Free · every trading day · 08:00 ET

Get the free 08:00 ET compute read by email, plus the AI Infrastructure Primer 2026.