Frontier AI datacentre
OpenAI Stargate UAE
0 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source1.00 GW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026SourceOpenAI Stargate UAE against the largest sites worldwide
| Site | Owner | Users | Country | Online now | Planned | Planned date |
|---|---|---|---|---|---|---|
| Microsoft Fairwater Wisconsin | Microsoft | OpenAI, Microsoft | United States | 369 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 2.26 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 13 May 2028 |
| Anthropic-Amazon New Carlisle | Amazon | Anthropic | United States | 910 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.93 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 17 Mar 2028 |
| OpenAI Stargate New Mexico | Oracle | OpenAI | United States | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.75 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 31 Dec 2028 |
| Meta Hyperion | Meta | Meta | United States | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.63 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1 Jan 2028 |
| Colossus 2 | SpaceXAI | Anthropic, Cursor, SpaceXAI | United States | 946 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.53 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 25 Feb 2027 |
| OpenAI Stargate Shackelford | Oracle | OpenAI | United States | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.40 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 11 Nov 2028 |
| QTS Cedar Rapids | Not stated | Not stated | United States | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.13 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 15 Nov 2027 |
| OpenAI Stargate UAE | G42 | OpenAI | United Arab Emirates | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.00 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1 Jan 2028 |
Site details
- Owner
- G42
- Users
- OpenAI
- Country
- United Arab Emirates
- IT power online now
- estimate at 16 Nov 2025
0 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source - Largest planned IT power
1.00 GW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source- Planned date
- 1 Jan 2028
Latest construction note
Building 1 and 2 are partly constructed. No clear evidence of more buildings starting construction.
Note from Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0).
Questions
Who owns OpenAI Stargate UAE?
Epoch AI's register lists G42 as the owner of OpenAI Stargate UAE, in the United Arab Emirates.
Who uses OpenAI Stargate UAE?
The register lists OpenAI as the users of the site.
How much power does OpenAI Stargate UAE have?
0 MW of IT power was online at the latest estimate in the register, against 1.00 GW planned, 0% of the plan (calculated). Snapshot of 14 Oct 2026.
When will OpenAI Stargate UAE be finished?
Epoch AI's timeline puts the site's largest planned IT power, 1.00 GW, at Jan 2028. Timelines are estimates and change as construction progresses.
Where does this datacentre data come from?
Epoch AI's Frontier Data Centers register (CC BY 4.0), which estimates each site's IT power over time from satellite imagery, permits and company statements. Figures are estimates, not company specifications.
Updated 14 Oct 2026. Source: Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0). Estimates, not company specifications. Methodology: Pipeline Tracker. Not investment advice.