Frontier AI datacentre
CoreWeave Denton TX
262 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source282 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026SourceCoreWeave Denton TX among the largest sites in the United States
| Site | Owner | Users | Country | Online now | Planned | Planned date |
|---|---|---|---|---|---|---|
| Microsoft Fairwater Wisconsin | Microsoft | OpenAI, Microsoft | United States | 369 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 2.26 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 13 May 2028 |
| Anthropic-Amazon New Carlisle | Amazon | Anthropic | United States | 910 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.93 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 17 Mar 2028 |
| OpenAI Stargate New Mexico | Oracle | OpenAI | United States | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.75 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 31 Dec 2028 |
| Meta Hyperion | Meta | Meta | United States | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.63 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1 Jan 2028 |
| Colossus 2 | SpaceXAI | Anthropic, Cursor, SpaceXAI | United States | 946 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.53 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 25 Feb 2027 |
| OpenAI Stargate Shackelford | Oracle | OpenAI | United States | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.40 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 11 Nov 2028 |
| QTS Cedar Rapids | Not stated | Not stated | United States | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1.13 GWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 15 Nov 2027 |
| CoreWeave Denton TX | CoreWeave | OpenAI | United States | 262 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 282 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 31 May 2027 |
Site details
- Owner
- CoreWeave
- Users
- OpenAI
- Country
- United States
- IT power online now
- estimate at 1 Sep 2026
262 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source - Largest planned IT power
282 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source- Planned date
- 31 May 2027
Latest construction note
Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.
Note from Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0).
Questions
Who owns CoreWeave Denton TX?
Epoch AI's register lists CoreWeave as the owner of CoreWeave Denton TX, in the United States.
Who uses CoreWeave Denton TX?
The register lists OpenAI as the users of the site.
How much power does CoreWeave Denton TX have?
262 MW of IT power was online at the latest estimate in the register, against 282 MW planned, 93% of the plan (calculated). Snapshot of 14 Oct 2026.
When will CoreWeave Denton TX be finished?
Epoch AI's timeline puts the site's largest planned IT power, 282 MW, at May 2027. Timelines are estimates and change as construction progresses.
Where does this datacentre data come from?
Epoch AI's Frontier Data Centers register (CC BY 4.0), which estimates each site's IT power over time from satellite imagery, permits and company statements. Figures are estimates, not company specifications.
Updated 14 Oct 2026. Source: Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0). Estimates, not company specifications. Methodology: Pipeline Tracker. Not investment advice.
Free · every trading day · 08:00 ET