Frontier AI datacentre
YTL Johor
113 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source284 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026SourceYTL Johor among the largest sites in Malaysia
Source: Compute Terminal AnalysisEpoch AI (CC BY 4.0)Methodology v0.9Updated 1 Nov 2026, 12:35 UTC
| Site | Owner | Users | Country | Online now | Planned | Planned date |
|---|---|---|---|---|---|---|
| DayOne Nusajaya | Not stated | Not stated | Malaysia | 473 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source | 473 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source | 2 Oct 2026 |
| DayOne Kempas | Not stated | Not stated | Malaysia | 422 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source | 422 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source | 1 Oct 2026 |
| YTL Johor | Not stated | Not stated | Malaysia | 113 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source | 284 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source | 1 Aug 2028 |
| Bridge Data Centres MY06 | ByteDance | ByteDance | Malaysia | 243 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source | 243 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source | 25 May 2025 |
Site details
- Owner
- Not stated
- Users
- Not stated
- Country
- Malaysia
- IT power online now
- estimate at 13 Jul 2026
113 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source - Largest planned IT power
284 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 1 Nov 2026Source- Planned date
- 1 Aug 2028
Latest construction note
Satellite imagery confirms Buildings 1 and 2 are structurally complete. Buildings 3 and 4 are underway, and construction equipment can be seen on the plot for Building 5. Extensive solar panel arrays have been built out.
Note from Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0).
Questions
How much power does YTL Johor have?
113 MW of IT power was online at the latest estimate in the register, against 284 MW planned, 40% of the plan (calculated). Snapshot of 1 Nov 2026.
When will YTL Johor be finished?
Epoch AI's timeline puts the site's largest planned IT power, 284 MW, at Aug 2028. Timelines are estimates and change as construction progresses.
Where does this datacentre data come from?
Epoch AI's Frontier Data Centers register (CC BY 4.0), which estimates each site's IT power over time from satellite imagery, permits and company statements. Figures are estimates, not company specifications.
Updated 1 Nov 2026. Source: Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0). Estimates, not company specifications. Methodology: Pipeline Tracker. Not investment advice.