Frontier AI datacentre
Huawei Horinger
184 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source346 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026SourceHuawei Horinger among the largest sites in China
| Site | Owner | Users | Country | Online now | Planned | Planned date |
|---|---|---|---|---|---|---|
| VNET Bayin Ulanqab | VNET | ByteDance | China | 221 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 700 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1 Sep 2027 |
| Huawei Wuhu | Huawei | Not stated | China | 157 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 457 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 1 Dec 2027 |
| Huawei Horinger | Huawei | Not stated | China | 184 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 346 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 14 Feb 2028 |
| Alibaba Zhangbei | Alibaba | Alibaba | China | 169 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 169 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 3 Jan 2026 |
Site details
- Owner
- Huawei
- Users
- Not stated
- Country
- China
- IT power online now
- estimate at 18 Aug 2026
184 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source - Largest planned IT power
346 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source- Planned date
- 14 Feb 2028
Latest construction note
On the east zone, building 6 is under construction, and potentially larger than any of the identically sized buildings constructed thus far. Building 3 has not begun construction.
Note from Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0).
Questions
Who owns Huawei Horinger?
Epoch AI's register lists Huawei as the owner of Huawei Horinger, in China.
How much power does Huawei Horinger have?
184 MW of IT power was online at the latest estimate in the register, against 346 MW planned, 53% of the plan (calculated). Snapshot of 14 Oct 2026.
When will Huawei Horinger be finished?
Epoch AI's timeline puts the site's largest planned IT power, 346 MW, at Feb 2028. Timelines are estimates and change as construction progresses.
Where does this datacentre data come from?
Epoch AI's Frontier Data Centers register (CC BY 4.0), which estimates each site's IT power over time from satellite imagery, permits and company statements. Figures are estimates, not company specifications.
Updated 14 Oct 2026. Source: Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0). Estimates, not company specifications. Methodology: Pipeline Tracker. Not investment advice.