Global AI Datacentre Monitor
AI datacentres in Sweden
0 MW
Epoch AI Frontier Data Centers (CC BY 4.0); sum of IT power online now calculated by Compute TerminalAs of 14 Oct 2026Source48 MW
Epoch AI Frontier Data Centers (CC BY 4.0); sum of planned IT power calculated by Compute TerminalAs of 14 Oct 2026SourceSites in Sweden, online now and planned
| Site | Owner | Users | Country | Online now | Planned | Planned date |
|---|---|---|---|---|---|---|
| EcoDataCenter 2 | Mistral AI | Mistral AI | Sweden | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 48 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 30 Jun 2028 |
Source: Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0), snapshot of 14 Oct 2026. Estimates, not company specifications.
Questions
How much AI datacentre capacity does Sweden have?
The 1 frontier AI datacentre in Epoch AI's register in Sweden have 0 MW of IT power online and 48 MW planned (sums calculated by Compute Terminal, 14 Oct 2026).
What is the largest AI datacentre in Sweden?
By planned IT power, EcoDataCenter 2 (Mistral AI): 48 MW planned, with 0 MW online at the latest estimate.
How many gigawatt-scale AI campuses are in Sweden?
0 of the 1 site in the register in Sweden plan 1 GW or more of IT power.
Where does this datacentre data come from?
Epoch AI's Frontier Data Centers register (CC BY 4.0), which estimates each site's IT power over time from satellite imagery, permits and company statements. Figures are estimates, not company specifications.
Updated 14 Oct 2026. Source: Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0); country sums calculated by Compute Terminal. Methodology: Pipeline Tracker. Not investment advice.