Frontier AI datacentre
Microsoft Narvik Norway
0 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source92 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026SourceMicrosoft Narvik Norway among the largest sites in Norway
| Site | Owner | Users | Country | Online now | Planned | Planned date |
|---|---|---|---|---|---|---|
| Microsoft Narvik Norway | Nscale | Microsoft | Norway | 0 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 92 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 31 Dec 2026 |
| CoreWeave Norway | CoreWeave | OpenAI | Norway | 42 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 42 MWEpoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source | 27 Jul 2025 |
Site details
- Owner
- Nscale
- Users
- Microsoft
- Country
- Norway
- IT power online now
- estimate at 5 Jul 2026
0 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source - Largest planned IT power
92 MW
Epoch AI Frontier Data Centers (CC BY 4.0)As of 14 Oct 2026Source- Planned date
- 31 Dec 2026
Latest construction note
Building 1 cooling looks complete. Backup generator install continues adjacent to B1. Building 2 cooling install continues. Backup generator concrete pads are there, but no equipment install visible. Cooling install appears to continue on Building 3. Construction equipment presen
Note from Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0).
Questions
Who owns Microsoft Narvik Norway?
Epoch AI's register lists Nscale as the owner of Microsoft Narvik Norway, in Norway.
Who uses Microsoft Narvik Norway?
The register lists Microsoft as the users of the site.
How much power does Microsoft Narvik Norway have?
0 MW of IT power was online at the latest estimate in the register, against 92 MW planned, 0% of the plan (calculated). Snapshot of 14 Oct 2026.
When will Microsoft Narvik Norway be finished?
Epoch AI's timeline puts the site's largest planned IT power, 92 MW, at Dec 2026. Timelines are estimates and change as construction progresses.
Where does this datacentre data come from?
Epoch AI's Frontier Data Centers register (CC BY 4.0), which estimates each site's IT power over time from satellite imagery, permits and company statements. Figures are estimates, not company specifications.
Updated 14 Oct 2026. Source: Epoch AI, Frontier Data Centers (epoch.ai/data/data-centers) (CC BY 4.0). Estimates, not company specifications. Methodology: Pipeline Tracker. Not investment advice.