News · · Neocloud contracts

Microsoft pulls out of Nscale's Loughton datacentre as grid connection slips to the 2030s

MicrosoftMSFTNVIDIANVDA

Microsoft has withdrawn from Nscale's planned datacentre in Loughton, Essex, after reports that grid power will not reach the site until the 2030s. Microsoft had planned to lease the full 50MW, which was to house about 23,000 Nvidia GB300 chips, the FT reported.

FOR: COMPUTE BUYER

Read the full article (Benzinga) (opens the original reporting in a new tab)Source 2 (Benzinga) (opens the original reporting in a new tab)Source 3 (Tech Times) (opens the original reporting in a new tab)Source 4 (Yahoo! Finance) (opens the original reporting in a new tab)Source 5 (Yahoo! Finance) (opens the original reporting in a new tab)

Our own summary with the key number, never article text; the source links to the original reporting. Each item is drafted automatically from its named sources and published once it passes our checks; the analyst reviews the items the checks hold, and errors are corrected and logged on the corrections page. Not investment advice.

All news

Get the CTI Compute Cost Index free in your inbox every morning.

By continuing you agree to the Terms of Subscription and the Terms of Use.