News · · Neocloud contracts

Kentucky Power seeks approval for 760-MW gas plant to serve TeraWulf's 1 GW Muskie Data Campus

TeraWulfWULF

Kentucky Power filed for regulatory approval of a gas facility beside Big Sandy in Louisa and a new EastPark substation, to serve up to 1 gigawatt of contracted demand in phases by 2029.

FOR: COMPUTE BUYERSINGLE SOURCE

Read the full article (Yahoo! Finance) (opens the original reporting in a new tab)Source 2 (Floyd County Times) (opens the original reporting in a new tab)

Our own summary with the key number, never article text; the source links to the original reporting. Each item is drafted automatically from its named sources and published once it passes our checks; the analyst reviews the items the checks hold, and errors are corrected and logged on the corrections page. Not investment advice.

All news

Get the CTI Compute Cost Index free in your inbox every morning.

By continuing you agree to the Terms of Subscription and the Terms of Use.